«STROYGAZMONTAZH» has started a pneumatic
testing of the Chusovoy-Berezniki-Solikamsk gas pipeline lateral (1st
string) under construction, on the "km 131 – km 160" portion.
The
reconstruction of the Chusovoy-Berezniki-Solikamsk gas pipeline lateral
of the L. Tura-Chusovoy-Perm trunk gas pipeline (1st and 2nd startup
complex) is performed for the needs of LLC «Gazprom Tsentrremont» by
such contractors as LLC «SGM» and «SU No.2» (OJSC).Installation and construction works are scheduled to be completed at the end of 2014. First startup complex covers 180-km gas pipeline construction, as well underwater crossings construction over the Vilva, Usva, Kosva and Yayva rivers.