Tuesday, 17 February 2015

"Gazprom" announced the purchase of pipes for the "Power of Siberia" for $ 1 billion


"Gazprom Komplektatsiya" announced a request for proposals for the supply of large diameter pipes for pipeline "The Power of Siberia" totaling $ 67.866 billion rubles. (including VAT). Delivery pipe will run throughout 2015, reports Interfax .

 The recipient of the order is LLC "Gazprom Transgaz Tomsk". Division is the customer highway construction. The total amount of purchases of more than 819 thousand. Tons. It will consist of 8 lots. Four of these weight ranges from 150 to 200 thousand. Tonnes.

 In early February, it was reported that "Gazprom" will not attract the general contractor in the construction of "Power of Siberia." The company decided to break the project into smaller lots. Earlier "Gazprom" preferred to distribute the Biggest lots.

 30 January "Gazprom" reported that potential bidders for the construction of the gas pipeline "The Power of Siberia" were 15 companies. Among them JSC "Stroytransgaz" Arkady Rotenberg. Among the potential bidders and companies' STG-AvtoTrans "," APS-West "," Argus Podvodstroy "," EVRAKOR "," APS-North "," Special Installation Argus "," Argus Swar Installation "," APS-East " "Spetsgazavtotrans", "Irkutskneftegazstroy", "Enterprise drilling", "Sibmost" and "SpetsMontazhProekt."

 In September, "Gazprom" and the Russian pipe plants have agreed on the terms of payment and delivery of pipes for the "Power of Siberia." The company has declared its readiness to advance up to 40% of pipes, and instead asked for a discount of 10% of their value. According to the analyst "VTB Capital" Alexander Donskoi, "Gazprom" will be spent on purchase of pipes and construction of a pipeline of about $ 56 billion.

 Through the pipeline "The Power of Siberia", whose length will be almost 4 thousand. Km, will be the transportation of gas from Yakutia and the Irkutsk region to other regions of Russia and China. February 17 Energy Minister Alexander Novak said that the contract for the supply of gas to China will be concluded in the coming months. "The challenge posed: do not tighten. In the coming months will finish reflect on this issue. We hope that in the next few months, the contract will be designed to the extent of signing ", - said the minister.

http://www.rbc.ru/rbcfreenews/54e34a109a7947404c6d3a48