Friday, 20 February 2015

"Rosneft" allow gas line "The Power of Siberia" in 2020

Starting the pipeline "Power of Siberia" on the resource base Chayandinskoye field in Yakutia is scheduled for 2018-2020 years. "Rosneft" and other independent gas producers can gain access to the pipeline in 2020-2025.




MOSCOW, February 20 - RIA Novosti / Prime. "Rosneft" and other independent gas producers in Russia may be able to transport gas from its fields through the pipeline, "The Power of Siberia" on the second phase of the project - in 2020-2025, it follows from the presentation Ministry of Energy.

Starting the pipeline "Power of Siberia" on the resource base Chayandinskoye field in Yakutia is scheduled for 2018-2020 years. In the second phase (2020-2025 years) in order to increase the supply of gas is connected Kovykta field in the Irkutsk region, as well as the field of "Rosneft" and independent gas producers.

Thus, the gas line can be connected to the field as Yurubcheno- Tokhomskoye, Kuyumbinsk and Sobinsk. After this power "Power of Siberia" in the second stage at the site of Chayanda Belogorska to grow to 60 billion cubic meters.

It is expected that the third phase (2025-2030 years), the volume of gas supplied from the fields offshore Sakhalin Island in the Primorsky and Khabarovsk Krai, replaced by resources provided by the GTS "The Power of Siberia." During this period, will be built the third section of the pipeline from Blagoveshchensk to Vladivostok with a capacity of 32 billion cubic meters of gas a length of 620 kilometers. The presentation is not specified whether the supply is made of independent producers to export or only on the domestic market.

In May 2014 the head of "Rosneft" Igor Sechin said that this is Russia's largest oil company, intends to become a major player in the gas market and, by 2030, be able to get on the fields east of the country 45 billion cubic meters of gas per year. To implement these volumes "Rosneft" is seeking access to the "Power of Siberia." The company appealed to the Ministry of Energy and the Government Commission on Energy with a proposal to build a pipeline to synchronize with the development of gas fields "Rosneft".

It follows that the pipeline "The Power of Siberia" will be built in three phases. The first to be built thread capacity of 32 billion cubic meters. m and a length of 2170 km to Belogorska with a branch to China. On it from 2018 to 2020 will be pumped gas condensate field Chayandinskoye.

At the second stage - from 2020 to 2025 - in order to increase the supply of gas to the gas pipeline connecting the Kovykta field, as well as deposits of "Rosneft" and independent gas producers. We are talking about Yurubcheno- Tokhomskoye, Kuyumbinskaya and Sobinsky gas fields. As a result of power "The Power of Siberia" in the second stage at the site of Chayanda Belogorska to grow to 60 billion cubic meters. m.

At the third stage - from 2025 to 2030 - will be built the third section of the pipeline from Blagoveshchensk to Vladivostok. Its capacity - 32 billion cubic meters. meters of gas and length - 620 km. At this stage, the volumes of gas supplied from the fields of the Sakhalin shelf in the Primorsky and Khabarovsk territories, will be replaced by gas supplied by "Power of Siberia."

In the presentation of the Ministry of Energy does not say whether the "Rosneft" to supply gas to yourself "Power of Siberia" in China, or will sell gas to "Gazprom".

Construction of the pipeline "The Power of Siberia", designed for Russian gas supplies to Yakutsk and Irkutsk gas production centers in the Far East of Russia and China on the "eastern route", began on September 1st. The pipeline - 3968 km. The estimated cost of its construction - 770 billion rubles.