Monday 30 March 2015

Timchenko company received a contract for the construction of "Power of Siberia"


The structure of Gennady Timchenko started to build the "Power of Siberia", without waiting for the contest
V.Sharifulin / TASS



JSC "Stroytransgaz" (STG; 31.5% in the Volga Group Gennady Timchenko) without competition received the first general contractor for the construction of the linear part of the pipeline "The Power of Siberia" from Russia to China. On Friday the general director of "Gazprom Transgaz Tomsk" (the customer of the project) Anatoly Titov at the annual meeting of the Russian Gas Society. It is about building the first section Chayanda - Lensk length of 208 km. This year STG Place the first 70-80 km pipe, said Titov. The contract value "framework", it "Draw" as the construction site, said a top manager. When construction began, he said. The representative of the growth hormone did not respond to calls. The representative of "Gazprom" on the request is not answered.

"Assignment" STG contractor for construction of the first section of "Power of Siberia" Titov explained the need not to disrupt the timing. "We had to redo the project in connection with import substitution, we are now forced to revise basic technical solutions, all flew away," - he said. In February, deputy chairman of "Gazprom" Andrey Kruglov said that the share of foreign exchange expenses of the company for investment projects is 21%. "Power of Siberia" 90-95% of the planned building of Russian equipment, Titov said on Friday. It is the replacement of imported communication systems and remote control.
Again with "Gazprom"

"Stroytransgaz" was founded in 1990. For many years he was the main contractor of "Gazprom", among its shareholders were relatives of Prime Minister Viktor Chernomyrdin and the Chairman of the concern Vyakhirev.Leading position the company lost in 2006, when "Gazprom" has sold its stake in "Stroytransgaz". New contracts from "Gazprom" group received only in 2012, bought the contractor "Argus Pipeline", which was renamed JSC "Stroytransgaz".

In the future, work with contractors will be conducted routinely on a competitive basis, assured Titov. Contests new plots the linear part of "Power of Siberia" can go in April and in the second half. A week ago, in an interview with "Vedomosti" head of the department of corporate management costs of "Gazprom" Mikhail Sirotkin said that "Power of Siberia" will be split into at least 10 sites, and all the competitions will be held before the end of the year. In this case, Sirotkin rejected that STG already is the general contractor, "It builds very large volumes, but to say that this is the main builder, probably not."

The official ceremony of start of construction of the pipe was held in September last year. The organizer of the ceremony is the structure of "SGM" Arkady Rotenberg. But after major orders began to receive growth hormone. In mid-September he received in a row without a tender worth at least 1.5 billion rubles. on the construction of the pier on the river Lena to receive goods from which to explore Chayandinskoye field (resource base "Power of Siberia"). The company also won a contract to build an access road to the mine by 18.5 billion rubles. In March, the company received two contracts - to 2.52 billion and 1.67 billion rubles., But after a tender for the construction of new roads and improvement of the Chayanda. Thus, the order book growth hormone on the "Power of Siberia" has already reached 24.19 billion rubles.But until now, it was only about the preparatory work and not on the construction of the pipe itself.

The length of the "Power of Siberia" by Chayanda to China will be 2136 km, reminded Titov. The total cost of the pipeline is estimated at 770 billion rubles. That is 360 million rubles. 1 km. Thus, for the construction of the STG Chayanda - Lensk can get almost 75 billion rubles. Sirotkin said that margin contractors "Power of Siberia" may be up to 20%. That is, growth hormone can earn 15 billion rubles., And contractors throughout the 'Power of Siberia "- 154 billion rubles.

Pipeline "Gazprom" continue to go up, indicating Director East European Gas Analysis Mikhail Korchemkin. The last major project of "Gazprom" in Russian - "Southern Corridor" worth 295 million rubles. 1 km, he calculated.