Customer: CJSC “Gazprom invest Yug"
Gas pipeline length: 36.8 kmPipe diameter: 325 mm
Pressure: 5.4 MPa
Construction completion: August 2014
In 2012 LLC "Stroygazmontazh" started the construction of
Tokarevka Zherdevka gas pipeline branch with its route passing through
the territory of Tambov and Voronezh Region.
In the course of construction three underground crossings under Kleshnya, Savala and Talovaya Rivers have to be formed by HDD method (with total length of 774 m), another six crossings under motor roads and two crossings under railway lines have to be formed using pipe-jacking technique (length of pipes is 534 m in total).
Moreover to provide stable operation of trunk gas pipeline the reliable system of telemechanics and communications will be arranged (consisting of control cables with length of 43 km, one radio relay station, two container-type units of backup power supply, three unmanned repeater stations and five control stations of telemechanics and communications).
In the course of construction three underground crossings under Kleshnya, Savala and Talovaya Rivers have to be formed by HDD method (with total length of 774 m), another six crossings under motor roads and two crossings under railway lines have to be formed using pipe-jacking technique (length of pipes is 534 m in total).
Moreover to provide stable operation of trunk gas pipeline the reliable system of telemechanics and communications will be arranged (consisting of control cables with length of 43 km, one radio relay station, two container-type units of backup power supply, three unmanned repeater stations and five control stations of telemechanics and communications).
No comments:
Post a Comment