Customer: CJSC "Gazprom invest Yug"
Gas pipeline length:360 km (1st and 2nd string)
Pipe diameter: 1020 mm
Pipe diameter (DN): 500 mm, 700 mm
Pressure: 5.4 МPa Construction completion: 4th quarter, 2014
Pipe diameter: 1020 mm
Pipe diameter (DN): 500 mm, 700 mm
Pressure: 5.4 МPa Construction completion: 4th quarter, 2014
Gas pipeline branches Chusovoy — Berezniki — Solikamsk have been
commissioned in 1970s — 80s. The reconstruction of these branches
covers the construction of two new gas pipelines in parallel
to currently operating strings.
In summer 2012 «Stroygazmontazh» started to work on a linear part of the firststart-up complex. The pipe-welding
base was installed in the area of Gremyachinsk town of Perm Territory
with over 100 units of construction equipment and 260 people mobilized
to the site. First start-up complex includes construction
of 180 km of gas pipeline in parallel to the second string of currently
operating gas pipeline Chusovoy — Berezniki — Solikamsk and construction
of underground crossings under Vilva, Usva, Kosva and Yayva Rivers. The
scheduled time limit for the completion of construction works within
1st start-up complex is 4th quarter, 2013.
The secondstart-up complex covers the construction
of 180 km of new gas pipeline and removal of the 1st string
of Chusovoy — Berezniki — Solikamsk gas pipeline.
It is planned to achieve the design capacity of Chusovoy — Berezniki — Solikamsk gas pipeline in 2014.
In summer 2012 «Stroygazmontazh» started to work on a linear part of the first
The second
It is planned to achieve the design capacity of Chusovoy — Berezniki — Solikamsk gas pipeline in 2014.